Construction Time Log

The following is a compilation of the time I've spent building my Bearhawk.  This is actual shop time (including making jigs and priming) but does not include time spent looking at the drawings, reading the CD, reading all of the Beartracks newsletters, researching the internet, ordering parts, etc.  This is strictly build time, from the time I pick up my tools until the time I set them down.  It is very accurate.

Construction Log

WING CONSTRUCTION

Category               Item completed                                                        

Total Hours Worked 

.

.

.
Jigs Wing Forms

  9.5 hours

Wing Ribs Nose ribs (46) (includes priming & stiffener angles)

52.5 hours

Wing Ribs Center Ribs (32) (includes priming and stiffener angles)

52.5 hours

Wing Ribs Back Ribs (4) ( includes priming)

  4.5 hours

Wing Ribs Flap (18) & Aileron (16)  Ribs (includes priming)

13.5 hours

Wing Ribs Aileron Nose(16) & Pocket Ribs(16) (includes priming)

13.5 hours

Wing Ribs Flap Nose Ribs (26) (includes priming)

  9.0 hours

Wing Ribs Tip Ribs (2) (includes priming and stiffener angles)

  4.0 hours

. . .
Wing Spars Main Wing Spars (includes priming & rib attach angles)

119.5 hours

Rear Spars Rear Spars (includes priming and rib attach angles)

73.5 hours

Wing Steel parts Wing Steel (includes sand blasting & priming)

118.5 hours

. . .
Wing Flaps Wing Flaps Assembled (includes priming)

 57.0 hours

Ailerons Ailerons Assembled (includes priming and balance tube)

 48.0 hours

Fabric Covering Covering Flaps/Ailerons (finished to Silver stage)

106 hours

. . .
Wing Assembly Wing Assembly (includes pulleys and rib assembly)

83.5 hours

Wing Skins Wing Skins (both wings)

242.0 hours

Control Fitting Fitting Ailerons & Flaps to Wings

40.0 hours

Fuel Tanks Fuel Tanks (includes construction,welding and fitting)

112.5 hours

Wing Tips Wing Tips

34 hours

Air Vents Air Vents

6 hours

. .
Total Time Wings

Both Wings (Complete includes wing tips)

1,225.0 hours

. . .



.

TAIL

Category Item completed Total Hours Worked 
Horz. Stabilizers Horizontal Stabilizers (includes mounting)

59 hours

Elevators (& trim tabs) Elevators and Trim Tabs (includes mounting & linkage)

68 hours

Rudder Rudder  (includes mounting)

29 hours

Vertical Stab Vertical Stabilizer

  8 hours

. . .
Total Time Empennage All Tail Surfaces (minus covering)

164 hours

. . .
.

FUSELAGE

.
Basic Fuselage Frame Fuselage Frame

115 hours

Main Landing Gear  Main Gear (including Brakes and Gear Struts)

    122.5 hours

Steps Entry Steps on Landing gear

18 hours

Tailwheel Assembly Tailwheel Assembly

 40 hours

Control Stick Assembly Control Sticks

39 hours

Rudder Pedals Rudder Pedal Assembly

37.5 hours

Flap Handle Flap Handle Assembly

18 hours

Elev. Bellcrank Elevator Bell Crank and Cables

21 hours

Door Flanges Door Flanges

19 hours

Seats Front and Rear seats

40 hours

Stringers Stringers

29 hours

Doors & Windows Doors & Windows includes latches & locks, skins

93 hours

Cargo Doors Cargo Doors includes latches and lock, skins

69 hours

Windshield Install Windshield

24 hours

Boot Cowl Boot Cowl and Tunnel

24 hours

Wing Fitting Fitting Wings to Fuselage

31 hours

Prime Fuselage Sandblasting and Painting Fuse frame

20 hours

Misc. Details Misc. Details

7 hours

. . .
Subtotal Fuselage  Fuselage Subtotal

767.0 Hours

. . .
.

Firewall Forward

.
Engine Mount Fabricated Engine Mount

32 hours

Firewall Firewall Fabrication

16 hours

Exhaust System Exhaust System

26 hours

Engine Cowl Engine Cowling

48 hours

Engine Controls Engine Controls and Heat Valve

24 hours

. . .
Subtotal Firewall Fwd Firewall Forward Subtotal

146 hours

. . .
.

Electrical Systems

Instrument Panel Instrument Panel

40 hours

Electrical Wiring Wiring (does not include Firewall Forward)

60 hours

. . .
. Electrical Subtotal

100 hours

. . .
.

Fuel and Brake Systems

.
Fuel System Fuel System plumbing

17 hours

Brake System Brake System

16 hours

. . .
. Brake and Fuel Subtotal

33 hours

. . .

Covering and Painting

Fabric Covering Fabric Covering Fuselage and Tail Pieces

174 hours

Painting Painting Fuselage and Wings

123 hours

. . .
. Covering and Paint Subtotal

297 hours

. . .
.

Interior

.
Seats and Belts Seats (includes front and rear and seat belts)

44 hours

Floorboards Floorboards and Baggage Bulkhead

16 hours

Misc Misc - install dome lights, install seat belts, etc.

29 hours

. . .
. Interior subtotal

89 hours

. . .
.

Grand Total All

.
Grand Total All

Grand Total all hours - aircraft completed May 10, 2008:

 2,821.0 hours