The following is a compilation of the time I've spent building my Bearhawk. This is actual shop time (including making jigs and priming) but does not include time spent looking at the drawings, reading the CD, reading all of the Beartracks newsletters, researching the internet, ordering parts, etc. This is strictly build time, from the time I pick up my tools until the time I set them down. It is very accurate.
WING CONSTRUCTION |
||
Category | Item completed | Total Hours Worked |
. | . |
. |
Jigs | Wing Forms | 9.5 hours |
Wing Ribs | Nose ribs (46) (includes priming & stiffener angles) | 52.5 hours |
Wing Ribs | Center Ribs (32) (includes priming and stiffener angles) | 52.5 hours |
Wing Ribs | Back Ribs (4) ( includes priming) | 4.5 hours |
Wing Ribs | Flap (18) & Aileron (16) Ribs (includes priming) | 13.5 hours |
Wing Ribs | Aileron Nose(16) & Pocket Ribs(16) (includes priming) | 13.5 hours |
Wing Ribs | Flap Nose Ribs (26) (includes priming) | 9.0 hours |
Wing Ribs | Tip Ribs (2) (includes priming and stiffener angles) | 4.0 hours |
. | . | . |
Wing Spars | Main Wing Spars (includes priming & rib attach angles) | 119.5 hours |
Rear Spars | Rear Spars (includes priming and rib attach angles) | 73.5 hours |
Wing Steel parts | Wing Steel (includes sand blasting & priming) | 118.5 hours |
. | . | . |
Wing Flaps | Wing Flaps Assembled (includes priming) | 57.0 hours |
Ailerons | Ailerons Assembled (includes priming and balance tube) | 48.0 hours |
Fabric Covering | Covering Flaps/Ailerons (finished to Silver stage) | 106 hours |
. | . | . |
Wing Assembly | Wing Assembly (includes pulleys and rib assembly) | 83.5 hours |
Wing Skins | Wing Skins (both wings) | 242.0 hours |
Control Fitting | Fitting Ailerons & Flaps to Wings | 40.0 hours |
Fuel Tanks | Fuel Tanks (includes construction,welding and fitting) | 112.5 hours |
Wing Tips | Wing Tips | 34 hours |
Air Vents | Air Vents | 6 hours |
. | . | |
Total Time Wings | Both Wings (Complete includes wing tips) |
1,225.0 hours |
. | . | . |
|
|
|
. | TAIL |
|
Category | Item completed | Total Hours Worked |
Horz. Stabilizers | Horizontal Stabilizers (includes mounting) | 59 hours |
Elevators (& trim tabs) | Elevators and Trim Tabs (includes mounting & linkage) | 68 hours |
Rudder | Rudder (includes mounting) | 29 hours |
Vertical Stab | Vertical Stabilizer | 8 hours |
. | . | . |
Total Time Empennage | All Tail Surfaces (minus covering) | 164 hours |
. | . | . |
. | FUSELAGE |
. |
Basic Fuselage Frame | Fuselage Frame | 115 hours |
Main Landing Gear | Main Gear (including Brakes and Gear Struts) | 122.5 hours |
Steps | Entry Steps on Landing gear | 18 hours |
Tailwheel Assembly | Tailwheel Assembly | 40 hours |
Control Stick Assembly | Control Sticks | 39 hours |
Rudder Pedals | Rudder Pedal Assembly | 37.5 hours |
Flap Handle | Flap Handle Assembly | 18 hours |
Elev. Bellcrank | Elevator Bell Crank and Cables | 21 hours |
Door Flanges | Door Flanges | 19 hours |
Seats | Front and Rear seats | 40 hours |
Stringers | Stringers | 29 hours |
Doors & Windows | Doors & Windows includes latches & locks, skins | 93 hours |
Cargo Doors | Cargo Doors includes latches and lock, skins | 69 hours |
Windshield | Install Windshield | 24 hours |
Boot Cowl | Boot Cowl and Tunnel | 24 hours |
Wing Fitting | Fitting Wings to Fuselage | 31 hours |
Prime Fuselage | Sandblasting and Painting Fuse frame | 20 hours |
Misc. Details | Misc. Details | 7 hours |
. | . | . |
Subtotal Fuselage | Fuselage Subtotal | 767.0 Hours |
. | . | . |
. | Firewall Forward |
. |
Engine Mount | Fabricated Engine Mount | 32 hours |
Firewall | Firewall Fabrication | 16 hours |
Exhaust System | Exhaust System | 26 hours |
Engine Cowl | Engine Cowling | 48 hours |
Engine Controls | Engine Controls and Heat Valve | 24 hours |
. | . | . |
Subtotal Firewall Fwd | Firewall Forward Subtotal | 146 hours |
. | . | . |
. | Electrical Systems |
|
Instrument Panel | Instrument Panel | 40 hours |
Electrical Wiring | Wiring (does not include Firewall Forward) | 60 hours |
. | . | . |
. | Electrical Subtotal | 100 hours |
. | . | . |
. | Fuel and Brake Systems |
. |
Fuel System | Fuel System plumbing | 17 hours |
Brake System | Brake System | 16 hours |
. | . | . |
. | Brake and Fuel Subtotal | 33 hours |
. | . | . |
|
||
Covering and Painting |
||
Fabric Covering | Fabric Covering Fuselage and Tail Pieces | 174 hours |
Painting | Painting Fuselage and Wings | 123 hours |
. | . | . |
. | Covering and Paint Subtotal | 297 hours |
. | . | . |
. | Interior |
. |
Seats and Belts | Seats (includes front and rear and seat belts) | 44 hours |
Floorboards | Floorboards and Baggage Bulkhead | 16 hours |
Misc | Misc - install dome lights, install seat belts, etc. | 29 hours |
. | . | . |
. | Interior subtotal | 89 hours |
. | . | . |
. | Grand Total All |
. |
Grand Total All | Grand Total all hours - aircraft completed May 10, 2008: |
2,821.0 hours |